New Tindo Solar Factory Construction

The new $6 million Tindo Solar factory is under construction with estimated completion by early 2021. This new facility will greatly increase our manufacturing capacity, bringing more Australian Made panels to Australians and increase exports of our proudly Australian product.

Weeks 31 & 32

While construction continued in the new Tindo office space, there was action on the outside of the building getting the painting and fixtures started

October 2020

This week’s timelapse video shows the construction of the new Tindo offices during the month of October. The construction of our new premises is very exciting and we look forward to being able to utilise our large facilities.

Week 28

Working on the racking in the new warehouse where we will be housing all our Australian Made panels.

Week 27

This week we moved the camera into the new warehouse. Getting the fittings ready to get the racking in.

Week 26

work continued on the building of the new Tindo manufacturing facilities and the installation of electrics in the warehouse – great footage of the crane at work

Week 25

The roof went onto the new Tindo factory.

Weeks 21 - 24

At the beginning of week 21 the electrical installations went into the warehouse and the ground was prepped for the driveway pour. Over the next 3 weeks the driveway was poured, SAPN transformer was installed and continued to put up the walls for the manufacturing facility.

Weeks 17 - 20

So much has happened in 4 weeks with the new warehouse nearing completion. The driveway has started to be laid and the walls for the new manufacturing facility have started going up. Exciting times in Mawson Lakes!

Weeks 13 - 16

More storm water drainage was installed and preparation of the site for the next slab.

Weeks 9 - 12

Completed the footings for the factory and office. Plumbing and services went in. Week 12 saw the slab for the office poured.

Weeks 5 - 8

Digging and pouring of concrete for the footings and the installation of the storm water detention tank.

Weeks 1 - 4

Building of the new Tindo Solar factory has started with preparation of the land and levelling the ground.

Learn More About Australian Made Solar





    *promotion ends 31st of December 2023, Terms & Conditions apply.
    20% Off, Plus Up To 48 Months Interest Free*
    SALE